Timber Frame Home progress, Lincoln, NH

The timber frame home site in Lincoln, New Hampshire is coming along nicely! The timber frame is scheduled for delivery September 23rd and the timber frame crew is waiting anxiously to put up the timber frame and T&G decking, which will take approximately four weeks. (The home is 3500 SF and has 300+ timbers.)


The timber exterior envelope will be structural insulated panels (SIPs), which are scheduled to deliver on October 13th and take about two weeks to install. Once the panels are on, the general contractor’s crew will put the roof on and install the Eagle windows into the pre-cut panels, completing the weather-tight shell.



Check back often for more progress updates and new site construction photos.


Kimberly Bonin, Executive Project Manager